# Configuration Changes
|
|
|
|
This process outlines how GNU will handle configuration changes. For a list of configuration changes, please see the [schedule](schedule.md)
|
|
|
|
## Infrastructure setup (2-4 weeks)
|
|
|
|
This is behind the scenes, when there is a need for a configuration change (upgrade or addition of a new platform), the first step
|
|
is to build a machine and work to get the OS working with taskcluster. This is work for hardware/cloud is done by IT. Sometimes
|
|
this is as simple as installing a package or changing an OS setting on an existing machine, but this requires automation and documentation.
|
|
|
|
In some cases there is little to no work as the CI change is running tests with different runtime settings (environment variables or preferences).
|
|
|
|
|
|
## Setting up a pool on try server (1 week)
|
|
|
|
The next step is getting some machines available on try server. This is where we add some code in tree to support the new config
|
|
(a new worker type, test variant, etc.) and validate any setup done by IT works with taskcluster client. Then Releng ensures the target tests
|
|
can run at a basic level (mozharness, testharness, os environment, logging, something passes).
|
|
|
|
|
|
## Green up tests (1 week)
|
|
|
|
This is a stage where Releng will run all the target tests on try server and disable, skip, fail-if all tests that are not passing or frequently
|
|
intermittent. Typically there are a dozen or so iterations of this because a crash on one test means we don't run the rest of the tests in the
|
|
manifest.
|
|
|
|
|
|
## Turn on new config as tier-2 (1/2 week)
|
|
|
|
We will time this at the start of a new release.
|
|
|
|
Releng will land changes to manifests for all non passing tests and then schedule the new jobs by default. This will be tier-2 for a couple reasons:
|
|
* it is a new config with a lot of tests that still need attention
|
|
* in many cases there is a previous config (lets say upgrading windows 10 from 1803 -> 1903) which is still running in parallel as tier-1
|
|
|
|
This will now run on central and integration and be available on try server. In a few cases where there are limited machines (android phones),
|
|
there will be needs to turn off the old config, or make the try server access hidden behind `./mach try --full`
|
|
|
|
|
|
## Turn on new backstop jobs which run the skipped tests (1/2 week)
|
|
|
|
Releng will turn on a new temporary job that will run the tests which are not green by default. These will run as tier-2 on mozilla-central and be sheriffed.
|
|
|
|
The goal here is to find tests that are now passing and should be run by default. By doing this we are effectively running all the tests instead of
|
|
disabling dozens of tests and forgetting about them.
|
|
|
|
|
|
## Handoff to developers (1 week)
|
|
|
|
Releng will file bugs for all failing tests (one bug per manifest) and needinfo the triage owner to raise awareness that one or more tests in their area need
|
|
attention. At this point, Releng is done and will move onto other work. Developers can reproduce the failures on try server and when fixed edit the manifest
|
|
as appropriate.
|
|
|
|
There will be at least 6 weeks to investigate and fix the tests before they are promoted to tier-1.
|
|
|
|
|
|
## move config to tier-1 (6-7 weeks later)
|
|
|
|
After the config has been running as tier-2 makes it to beta and then to the release branch (i.e. 2 new releases later), Releng will:
|
|
* turn off the old tier-1 tests (if applicable)
|
|
* promote the tier-2 jobs to tier-1
|
|
* turn off the backstop jobs
|
|
|
|
This allows developers to schedule time in a 6 weeks period to investigate and fix any test failures.
|